(Completed) Tender Requirements for the Construction of the Automated Storage and Retrieval System Steel Structure and Connecting Walkways for the Pharmaceutical Integration and Innovation Development Demonstration Project of Hebei Guolong Pharmaceutical Co., Ltd.
Category:
Time: 2025-07-19
Hebei Guolong Pharmaceutical Co., Ltd. Demonstration Project for Integrated and Innovative Development in the Pharmaceutical Industry
Tender Requirements for the Construction of the Automated Storage and Retrieval System Steel Structure and Connecting Walkways
Project Number:
Project Name: Demonstration Project for Integrated Pharmaceutical Development and Innovation at Hebei Guolong Pharmaceutical Co., Ltd.
Automated Storage and Retrieval System Steel Structure and Connecting Corridor Project
Recruitment Mark Person: Shijiazhuang Sihua Pharmaceutical Co., Ltd.
Date: 2025 year 7 month 17 Day, please at 7 month 25 Recently submitted the tender document list and verified qualifications.
Entrusting Agency: None
One : Project Overview:
The civil engineering foundation works for the automated storage and retrieval system (AS/RS) of the Pharmaceutical Integration and Innovation Development Demonstration Project of Hebei Guolong Pharmaceutical Co., Ltd. are located on newly acquired land within the company’s premises, at the northern end of Sanxia Road and the eastern side of Xingye Street in the Shijiazhuang Economic and Technological Development Zone. This tender covers both the AS/RS and the connecting corridor.
Automated storage and retrieval system, Gross floor area 21358 square meter , a single-story steel-structure automated storage facility on the ground level. Connecting corridor 4 70 square meters. Currently, the construction site is overgrown with weeds and uneven. The area surrounding the site is generally level and can be used as a construction site.
Two : Scope of Tender:
This tender covers the primary and secondary steel structural components, as well as the roof and wall enclosure system—including aluminum composite panel cladding for parapet walls—of the architectural and structural drawings issued by Party A, along with the structure and exterior cladding of the connecting corridors. Scope includes the connection between the steel superstructure and the substructure, fabrication and installation of primary and secondary steel structures, transportation, anti-corrosion and fire-retardant coating, fabrication and installation of steel platforms and canopies, detailing and finishing of door and window openings, and fabrication and installation of roof-mounted ventilation units (with electric actuation). Additionally, it encompasses the opening, capping, and finishing work required for the connection between the corridor and the existing automated warehouse (for which no detailed drawings are provided, design shall be undertaken independently), as well as special construction operations such as hot work and working at heights on the southern section of the corridor, which is located within Party A’s southern plant area; such operations necessitate the completion of the requisite permits and approvals, and all construction personnel must hold valid high-altitude work certificates and welding qualifications, and have 120 Commercial accident insurance for ten thousand people. In other specialized drawings, any reserved and embedded works that are to be constructed concurrently—such as siphonic rainwater drainage in the plumbing and drainage drawings and roof lightning protection grounding in the electrical drawings—shall include the installation of lightning protection and grounding down conductors. Upon completion, the construction site shall be cleaned up, with all waste and temporary structures removed and transported offsite, and the original terrain restored. One-time comprehensive cleaning of the exterior walls (including exterior windows) and interior spaces (including structural components).
This tender does not include: foundation works (piles), masonry works, concrete structural works, flooring, and the procurement and installation of all doors and windows.
Three : Construction Schedule Requirements 100 Heaven
Upon signing the contract, a penalty shall be imposed for each day of delay in the construction period due to non-force majeure reasons. 5000 One yuan exactly.
Four : Qualification Requirements
Grade-I steel structure construction; Grade-A design.
Five : Tendering method:
1、 This project will be tendered using a bill-of-quantities approach. Bidders shall, based on the construction drawings provided by the employer, independently calculate the bill of quantities, which shall include a list of construction items, a schedule of main materials, a comprehensive unit-price analysis table, a schedule of provisional works, and other relevant documents. Costs for safe and civilized construction shall be itemized separately. The evaluation criteria comprehensively consider the bidder’s quotation and construction schedule, construction plan, technical level, staffing, and other factors. 。
2、 Upon receipt of the notification, the bidder shall obtain the tender requirements and construction drawings; upon receipt of the drawings, 8 Complete the preparation of the tender documents within [number] days, seal and affix the official stamp to the tender package, and submit one original and one copy. Upon receipt of notification from Party A, submit the tender within the prescribed time limit.
Bidders are required to pay a bid bond. 20 Accounts with balances of RMB 10,000 or less:
Account Name: Hebei Guolong Pharmaceutical Co., Ltd.
Bank of Account Opening: Agricultural Bank of China, Gaocheng Liangcun Development Zone Sub-branch
Account: 50-314901040021214 (Please indicate “Stereo Warehouse Steel Structure Bid Bond” in the remarks.)
Upon bid opening, the deposit shall be refunded to Party A; however, it shall not be refunded to the winning bidder and will instead be converted into a construction security deposit, which will be refunded upon completion of the construction works within the scope of the contract and subsequent acceptance.
3 On the day of bidding, the bidder shall submit to Party A for verification the original copies of its business qualifications, the original power of attorney issued by the legal representative, and the bidder’s identity documentation. The tender document shall include photocopies of valid qualification documents, such as copies of the enterprise’s business qualifications, safety qualifications, and certificates confirming that no outstanding wages are owed to migrant workers.
Six : Contract Requirements:
1. This project is governed by a lump-sum contract, under which the total contract price is fixed and final; following the execution of the contract, neither the unit prices nor the quantities listed in the bill of quantities shall be adjusted. In the event of scope changes attributable to Party A, the quantity of work subject to such changes shall be calculated based on the drawing revisions confirmed in writing by Party A, and the unit prices shall be those specified in the tender bill of quantities. No calculation shall be made for provisional items, taxes, and government fees, etc. ,(If there is a total-price discount, the unit price shall be calculated by applying the total-price discount rate); if no unit price is specified in the bill of quantities, the unit price shall be determined based on the unit prices and related item analyses for similar engineering works in the bill of quantities; if no similar items are available, the calculation shall be made in accordance with Hebei Province. 2012 The unit-price direct costs shall be priced, with no provision for contingency or other charges. Any changes resulting in a reduction of the scope of work shall be adjusted accordingly on an actual-cost basis.
2、 This quotation is based on optimized bids submitted by each vendor; the optimized drawings must be approved and stamped by Party A’s design institute. In principle, the main structural components shall not be optimized; however, purlins, column braces, and bracing members may be optimized by using hot-dip galvanized components that are bolted on-site.
3 1. This project is proposed to be executed on a turnkey, materials-included basis, with the bidder responsible for all primary and secondary materials.
4、 Payment for this project: All payments for this project shall be Bank Accepted bill of exchange , a prepayment of the contract price shall be made upon signing the contract. 20% , payment of the contract price shall be made upon the arrival of all main structural components. 20% , upon arrival of all roof panels and commencement of installation, payment shall be made according to the contract price. 20% , upon completion of all works and passing the final acceptance inspection, payment shall be made up to the total settled price of 95% , remaining 5% For the warranty deposit, full 18 Payment shall be made in full after one month, provided there are no quality issues. Prior to each payment, the contractor shall submit an invoice for the same amount. 9% Special VAT invoice), payment to 95% Upon completion of each milestone, the warranty deposit invoice shall be issued concurrently.
5 The quotation includes all costs required for construction. 。
7. Construction Requirements:
The contractor must carry out construction in accordance with the drawings and code requirements. 。
1. Steel Structure Engineering: The primary and secondary structural materials are sourced from Shougang, Baosteel, Angang, Baogang, Pangang, Tangsteel, and Handan Iron & Steel.
2. Steel structure painting requirements: Use Qilu or Chenyang water-based paint, with a coating thickness in accordance with the design drawings. Fire-resistant coatings shall be supplied by Jinyu, Qilu, or other brands approved by Party A.
3. Wall system: The wall uses 100 Thick concealed-nail wall panels, manufactured by Shandong Wanshida. Both the inner and outer face sheets of the panel use base materials from Baosteel and BOSG. The core insulation material is rock wool, with designated brands being Jinyu and Owens Corning, and a density of no less than 120KG/m ³.
4. Roofing system: The roofing system adopts through FM For certified products, Butler or Lysaght Pittsburgh should be given priority for roofing systems. 360 Vertical seam-locked profiled panels (with sliding supports), fabricated using a dedicated seam-locking machine; the seam joints are pre-sealed with sealant at the factory. The original contract between the contractor and Butler or Laisi Company shall be retained by Party A. If other brand roofing systems are to be used, prior consultation is required (not less than 360 Install standing-seam roofing on-site using a dedicated seam-locking machine. The roof insulation shall be glass wool, with specified brands including Jin Haiyan, Owens Corning, and Huamei Meiles. The contractor is responsible for the procurement and installation of the roofing system. 304 Stainless steel fan (electric), roof gutters shall adopt 304 Stainless steel material, thickness 3 mm The canopy’s inner and outer panels are flush with the roof.
5. Stormwater pipe project: All stormwater pipes shall be采用 High-Density Polyethylene Material:选用 Zhongcai or Liansu brand, pressure-resistant. 1.6 M pa 。
6. Door and Window Works: All doors and windows shall be procured and installed by Party A; the Contractor shall be responsible for edge finishing and joint sealing. Adopt Thick 0.6 mm Fabrication and fabrication of roll materials with the same material and coating as the wall panels. 。
7. Pre-embedded Works: The Bidder shall, in accordance with the architectural, structural, electrical, HVAC, and plumbing & drainage drawings issued by the Employer, install and embed conduit, junction boxes, distribution panels, lightning down conductors (including roof flashings), and grounding facilities. All pipes and conduits that pass through roofs and walls shall be provided with waterproof and fire-resistant treatment.
8. Weather-resistant sealant uses Dow or United States SIKE 。 Waterproof tape, sealant paste : The sealant mortar uses imported, construction-specific adhesive, with a material composition of 100% Silicone rubber is used, and imported waterproof tape specifically designed for color-coated panel joints is applied at the lap joints between panels. Butyl rubber is sourced from Lianjie Chemical (Kunshan). External adhesive: 8509 , internal adhesive: 8506。 Self-tapping screws use Biaodi. , Yingfeng Screw 。 High-strength bolts are used. 8.8/10.9-grade torsional-shear high-strength bolts with black oxide finish; the remaining bolts are galvanized Class C bolts, manufactured by Shanghai Gaoqiang and Changjiang Fasteners. 。
9. All purlin supports, purlins, and bracing installed on the main structure shall be connected by bolts; welding is prohibited. The purlin material shall be continuously hot-dip galvanized coil produced in the factory. board 。
10. Roof-mounted fan openings must be fitted with roof opening supports, which shall be fabricated by factory welding of aluminum alloy plates. One entity become type , with rigid insulation blocks installed on the interior. Manufacturer: Haifude. The expansion joints between the connecting corridor and the two automated storage systems are constructed using prefabricated aluminum alloy expansion joints.
VIII. Quality Warranty
The warranty period for the main structural works of this project shall be equal to the design service life; the warranty periods for waterproofing and rainwater drainage pipes are as follows: 25 Year, the warranty period for roofs and walls is 25 During the warranty period, the contractor shall provide free repair for quality issues arising from non-human factors. However, any losses incurred by Party A due to water leakage or other problems caused by such quality issues shall be borne by the bidder. The amount of such losses shall be determined based on the original purchase invoice or the contract price; for Party A’s own products, the calculation shall be based on the sales price stated on Party A’s invoice.
Nine 1. Bid submission date: Tentative 2025 year 7 month 30 day
The Contractor shall be solely responsible for resolving all patent-related issues arising from the technical solutions employed during construction, and Party A shall bear no associated costs. All issues arising during construction, including coercive buying and selling and local protectionism, shall be resolved by the contractor. All applicable fees and charges that must be paid to the relevant government authorities during construction shall also be borne and settled by the contractor. This includes the fees for completion-handover procedures, which shall be borne by the steel structure contractor insofar as they pertain to the steel structure.
X. Construction power and water supply are located at the southeast corner of the plant site. Bidders shall specify the required electrical load in their tender documents and shall independently arrange for the necessary cables and water pipes. Utility meter readings shall be taken, and the monthly bills shall be submitted to Party A.
Eleven, During construction, all works that Party A subcontracts on its own—including, but not limited to, fire protection and electrical installation—shall be provided with construction sites and work areas by the steel structure contractor, who shall not charge the subcontractors any fees. Any documentation required to be submitted to government authorities shall be compiled by the steel structure contractor and handed over to the civil engineering contractor; for documents requiring official seals, the general contractor shall affix such seals. The civil engineering contractor shall be responsible for the overall as-built documentation. In connection with the foregoing, the civil engineering contractor shall not levy any coordination or management fees. The steel structure contractor must fully cooperate with the civil engineering contractor in handling the aforementioned procedures and preparing the relevant documentation.
Steel structure Partial structure Detection The costs shall be borne by the bidder.
Shijiazhuang Sihua Pharmaceutical Co., Ltd.
Technology Improvement Department
2025 year 7 month 17 day
Keywords:
More Announcements
SERVICE HOTLINE
Address: Shimen Building, No. 8 Xingye Street, Shijiazhuang Economic and Technological Development Zone
Tel.: +86-311-67167130
Email: office@sjzsiyao.com
Mobile site
E code